๐Ÿ‘‰๐ŸปMost standard form construction contracts contain provisions prescribing a strict form of notice required to be submitted by the contractor in case of a claim for extension of time.

Exampls –
Sub-Clause 20.1 read with sub-clause 8.4 of the fidic Conditions of Contract (Silver Book)
๐Ÿ‘‰๐Ÿป..the contractor must give a detailed notice to the employer within 28 days of the contractor becoming aware or from the date when the contractor should have been aware of any such event. The failure to give such notice would result in extinguishment of the rights of the contractor.

Legal Position in India:
๐Ÿ‘‰๐Ÿป It can be argued that strict notification clauses may get hit by Section 28 of the Indian Contract Act 1872.

Section 28 provides:
๐Ÿ‘‰๐Ÿป โ€œ28- Agreements in restraint of legal proceedings void โ€“ Every Agreement

a. by which any party thereto is restricted absolutely from enforcing his rights under or in respect of any contract, by the usual legal proceedings in the ordinary tribunals, or which limits the time within which he may thus enforce his rights; or

b. which extinguishes the rights of any party thereto, or discharges any party thereto, from any liability, under or in respect of any contract on the expiry of a specified period so as to restrict any party from enforcing his rights, is void to the extent.โ€ฆโ€

Thus, in view of above, such notification clause may become void under Indian law.

In the case of Chander Kant and Co. v. Vice Chairman, DDA,74

๐Ÿ‘‰๐Ÿป the Delhi High Court held that both curtailment of the period of limitation for specific period and extinction of the right are not permissible under Section 28 and if there is any clause to that effect in an agreement it would be barred under law.

The Supreme Court , in the case of
Union of India and Ors v. IndusInd Bank Ltd. and Ors.,

๐Ÿ‘‰๐Ÿป held that โ€œeven where an agreement extinguishes the rights or discharges the liability of any party to an agreement, so as to restrict such party from enforcing his rights on the expiry of a specified period, such agreement would become void to that extent…โ€.

Denounce with righteous indignation and dislike men who are beguiled and demoralized by the charms pleasure moment so blinded desire that they cannot foresee the pain and trouble.

Latest Portfolio

Need Any Help? Or Looking For an Agent

ยฉ Adroit PMC 2024. All Rights Reserved.
Disclaimer

This website has been designed only for the purposes of dissemination of basic information on ADROIT; information which is otherwise available on the internet, various public platforms and social media. Careful attention has been given to ensure that the information provided herein is accurate and up-to-date.

This website is not an attempt to advertise or solicit clients and does not seek to create or invite any lawyer-client relationship. The links provided on this website are to facilitate access to basic information on ADROIT, and, to share the various thought leadership initiatives undertaken by it. The content herein or on such links should not be construed as a legal reference or legal advice. Readers are advised not to act on any information contained herein or on the links and should refer to legal counsels and experts in their respective jurisdictions for further information and to determine its impact.

Terms of use andย Privacyย policy