Case Title: Government of NCT of Delhi v. R.S. Sharma Contractors Pvt Ltd, OMP(COMM) 130 of 2023, Date: 16.08.2023

Facts


👉The parties entered into an agreement dated 13.09.2014 by which the respondent/contractor was entrusted with the work of widening of a bridge. The work was to be completed within 18 months. Clause 5 of the agreement provided for extension of time in certain situations where the delay was not attributable to the contractor.

👉There was a delay in the execution of the project work and certain extension of times were sought by the respondent and granted by the petitioner. It is noteworthy that the respondent had given an undertaking not to make any claims for the extended period of project. However, disputes arose between the parties w.r.t payments under the final bill. Accordingly, the respondent invoked the arbitration.

👉The arbitrator, vide the impugned award, allowed the claims of the respondent by holding the petitioner liable for the delays in the completion of the project work. The tribunal rejected the contention of the petitioner that the claims were not maintainable as the respondent had executed an NCC in favour of the petitioner forgoing its claims. The tribunal held that the NCC was executed under duress as respondent’s bills were pending and the retention money was lying with the petitioner, and it was a pre-condition to the EOT.

Sequitur by the Court:


👉The Court observed that the arbitral tribunal has categorically held the petitioner liable for causing the delay in the completion of the project work and that this finding of the tribunal remains unchallenged.


👉The Court held that issuance of NCC or other similar ‘no claim’ certificate by a party, in favour of another contracting party, by itself does not disentitle the party having a claim from explaining the circumstances in which NOC is issued. Reverse of the same is equally true. There is no absolute rule which outrightly negates the evidentiary value of NOC’s or ‘no claim’ certificate. It can’t be said that in every case NOC or ‘no claim’ certificate should be treated as unreliable evidence and the giver of the certificate enjoys some sort of immunity in law that will save his rights despite issuance of a ‘no claim’ certificate.

👉Rather, issuance of ‘no claim’ certificate must be treated as prima facie evidence against the issuer of such certificate, and a heavy burden must be cast upon him to prove that the same was not given voluntarily.

👉The Court further held that mere absence of an escalation clause would not preclude a party from claiming escalation, as a measure of damages suffered by it, if the other party is guilty of causing delays in the completion of the work. Accordingly, the Court dismissed the challenge

#delhihighcourt #arbitration #claim #court #eot

Denounce with righteous indignation and dislike men who are beguiled and demoralized by the charms pleasure moment so blinded desire that they cannot foresee the pain and trouble.

Latest Portfolio

Need Any Help? Or Looking For an Agent

© Adroit PMC 2024. All Rights Reserved.
Disclaimer

This website has been designed only for the purposes of dissemination of basic information on ADROIT; information which is otherwise available on the internet, various public platforms and social media. Careful attention has been given to ensure that the information provided herein is accurate and up-to-date.

This website is not an attempt to advertise or solicit clients and does not seek to create or invite any lawyer-client relationship. The links provided on this website are to facilitate access to basic information on ADROIT, and, to share the various thought leadership initiatives undertaken by it. The content herein or on such links should not be construed as a legal reference or legal advice. Readers are advised not to act on any information contained herein or on the links and should refer to legal counsels and experts in their respective jurisdictions for further information and to determine its impact.

Terms of use and Privacy policy